LOCATION
MILLIKEN STATION, LANSING NY

CAPACITY
300 MW

PROJECT FUNDING
TOTAL $158,607,807 100%
DOE $ 45,000,000 28%
PARTICIPANT $ 113,607,870 72%

  • ACHIEVE SO2 CAPTURE EFFICIENCY
  • NOX TO CLEAN AIR COMPLIANCE
  • MAINTAIN STATION EFFICENCY
  • ELIMINATE WATER DISCHARGE
  • S-H-U FGD PROCESS
    (SAARBERG-HOLTER-UMWELTTECHNIK)
  • 98% SO2 REMOVAL
  • PRODUCE WALL-BOARD GRADE GYPSUM